Do you need this or any other assignment done for you from scratch?
We have qualified writers to help you.
We assure you a quality paper that is 100% free from plagiarism and AI.
You can choose either format of your choice ( Apa, Mla, Havard, Chicago, or any other)
NB: We do not resell your papers. Upon ordering, we do an original paper exclusively for you.
NB: All your data is kept safe from the public.
1. Make all revisions as suggested when I reviewed your previous lab submission.
1. Make all revisions as suggested when I reviewed your previous lab submission. Do not re-submit your file with the same mistakes as this will affect your score.
2. Use the Resource Sheet in Microsoft Project to create a resource pool. The resource pool is the list of resources that you will need to carry out your project activities, including people working on your project. When the Max-Units value is other than 100%, enter a resource note to explain your scheme. (1 point)
3. Assign a standard rate for each resource as appropriate. Enter an overtime rate if you are planning for some of your project personnel to work overtime – this is optional. Entering pay rates allows Microsoft Project to calculate resource and activity costs for you. (1 points)
4. Assign resources to all project activities that require resources; note that resources are NOT added to Summary tasks and usually not to milestones. Remember, project activities without resource assignments will not be performed. So you want to ensure that every activity that requires resources has a resource assignment. (2 points)
5. When assigning resources, make sure that activity durations remain the same, unless you want them to change. Review your Project Statistics before and after resource assignments to document any change in your project duration. What did you see? Add a task note in Task Zero to share your observation. (1 points)
6. Review your resource allocation and resolve all over allocations if there are any. If you believe that an over allocation is reasonable and does not need to be leveled, please add a resource note to explain why. Your explanation has to be realistic. (2 points)
7. Switch to the Gantt Chart view, apply the Cost table, and note the total cost of the project. Remember, in MS Project, Task Zero is the project, unless you purposed structured your plan for task 1 to represent the entire project. Calculate 10% of the total cost of the project and add the amount as contingency reserve to your project (see below instructions on how to add contingency reserve in MS Project). Enter a note in Task zero to indicate the total cost of your project. (2 points)
8. If you have developed your plan as fully as possible and you are satisfied with it, save a baseline. Remember, the contingency reserve must be included in the baseline. This is an important task as this baseline will serve as a basis for evaluating your project performance. You cannot effectively monitor progress without the baseline plan. (1 points)
9. Mark all your initiating and planning activities 100% complete. (2 points)
10. Set the status date of your project to exactly half way through since the project has started (your project start date should coincide with the first working day of the start of this section of the class). From the Task tab, in the Schedule group, Select all of the Executing tasks and then click on Mark on Track. (1 points)
11. Open the Tracking table. Review the percentage complete for each of the tasks that have at least some progress.
12. Using the Tracking table with a split screen combination view, enter Actual Start and/or Actual Finish dates that are different from the planned dates for at least 5 tasks. (Hint: Change only Actual Start and Actual Finish values – Do not change baseline values). (2 points)
13. Using the Tracking table with a split screen combination view, enter Actual Durations that are different from the planned durations for at least 3 other tasks. Add a task note to at least one of these tasks explaining why the duration might have changed. (Hint: Change only Actual duration values – Do not change baseline values) (2 points)
14. View the Project Statistics to see how much variance you have from the original baseline for your project. You can also analyze project variances using the Earned Value table. You will have the opportunity to cover earned value management techniques extensively in more advanced project management courses.
15. Based on what you saw in question 14, how do you predict this project will end in terms of schedule and cost variances? Provide your forecasts in the submission area in Canvas (Hint: Assignment Submission>Write Submission or Add Comments in Canvas). Forecasts and predictive analysis rely on data – not feelings or opinions. (2 points)
16. Display the Resource Usage view and save your file so that it automatically opens in that view. (1 point)
Save and submit your Microsoft Project file in the Resource Usage view to your instructor. This assignment is due no later than the TENTH week of the class.
For lab assignment 3, watch these videos:
https://youtu.be/SLvIfRM_TloLinks to an external site.
https://youtu.be/W8OsKFmtheYLinks to an external site.
https://youtu.be/EcKfe9pMj4MLinks to an external site.
Hints:
1) When a resource refers to a specific person (e.g., Fred Shaw or Jane Boyd), the Max.Unit column should not exceed 100%; that is, full time. For a resource scheduled to work less than full-time, you can enter a smaller maximum-units value.
2) When a resource represents a group of people with common skills such as engineers, plumbers, electricians, carpenters, editors, and writers, you can enter a maximum-units value that is higher than 100%. For example, the resource engineers entered with 400% max-units means that you are planning to have 4 engineers working full time on your project.
3) Apply the Resource Usage view to check for activities without resource assignments.
4) Review the sections listed below from the HBSP tutorial to understand various cost categories that your project might generate:
5) In MS project, reserves may be added as follows:
a) From the Resource Sheet view in MS Project, create a “Cost resource” named “Contingency Reserve.” The contingency reserve is treated here as a fixed overhead to the project.
b) Make sure to choose “cost” as the resource type. Next, you will need to switch to the Gantt chart view.
c) From the Gantt chart view, select a work package or activity to which you want to assign the contingency reserve.
d) From the resource tab, click Assign resources and select Contingency Reserve from the Assign Resources dialog box
e) Enter the amount of contingency reserve you calculated.
f) Repeat the process for each task to which you wish to assign a contingency amount.
g) Finally, switch to the Task Usage view to examine where reserves were added to your project.
Save your work and submit your Microsoft Project file to your instructor via the appropriate link.
This assignment is due no later than Sunday of the TENTH week of the class. E-mail submission will be rejected.
Do you need this or any other assignment done for you from scratch?
We have qualified writers to help you.
We assure you a quality paper that is 100% free from plagiarism and AI.
You can choose either format of your choice ( Apa, Mla, Havard, Chicago, or any other)
NB: We do not resell your papers. Upon ordering, we do an original paper exclusively for you.
NB: All your data is kept safe from the public.
Place this order or similar order and get an amazing discount. USE Discount code “GET20” for 20% discount